DateScheduledTrains RunOn TimeWithin 5 min.Comments
Wednesday 01162162(100.0%)122(75.3%)140(86.4%) 
Thursday 02162162(100.0%)144(88.8%)157(96.9%) 
Friday 03162162(100.0%)131(80.8%)150(92.5%) 
Saturday 04163163(100.0%)119(73.0%)150(92.0%) 
Sunday 056262(100.0%)58(93.5%)62(100.0%) 
Monday 06162154(95.0%)112(69.1%)130(80.2%)A broken down train between Garswood and Bryn resulted in diversions, delays and cancellations from 12:30 until about 15:00.
Tuesday 07162161(99.3%)138(85.1%)154(95.0%) 
Wednesday 08162162(100.0%)141(87.0%)157(96.9%) 
Thursday 09162162(100.0%)141(87.0%)157(96.9%) 
Friday 10162162(100.0%)138(85.1%)154(95.0%) 
Saturday 11163163(100.0%)139(85.2%)160(98.1%) 
Sunday 126262(100.0%)55(88.7%)60(96.7%) 
Monday 13162162(100.0%)139(85.8%)157(96.9%) 
Tuesday 14162162(100.0%)138(85.1%)153(94.4%) 
Wednesday 15162161(99.3%)142(87.6%)160(98.7%) 
Thursday 16162162(100.0%)126(77.7%)156(96.2%) 
Friday 17162162(100.0%)135(83.3%)156(96.2%) 
Saturday 18163163(100.0%)125(76.6%)148(90.7%) 
Sunday 196262(100.0%)60(96.7%)62(100.0%) 
Monday 20161161(100.0%)120(74.5%)140(86.9%)A broken down train at Huyton caused delays and cancellations between 09:30 and 11:00.
Tuesday 21160159(99.3%)141(88.1%)155(96.8%) 
Wednesday 22160160(100.0%)135(84.3%)151(94.3%) 
Thursday 23160158(98.7%)124(77.5%)145(90.6%) 
Friday 24162160(98.7%)109(67.2%)132(81.4%) 
Saturday 25163163(100.0%)134(82.2%)148(90.7%) 
Sunday 266262(100.0%)59(95.1%)61(98.3%) 
Monday 27161161(100.0%)134(83.2%)153(95.0%) 
Tuesday 28161161(100.0%)134(83.2%)152(94.4%) 
Wednesday 29161161(100.0%)142(88.1%)159(98.7%) 
Thursday 30161161(100.0%)118(73.2%)140(86.9%)Delays to Blackpool services between 13:00 and 18:00 were caused by an incident at Leyland.
Friday 31162162(100.0%)133(82.0%)149(91.9%) 
Month46154600(99.6%)3801(82.3%)4323(93.6%) 

Notes
  1. The figures are derived from information of Network Rail Infrastructure Limited licensed under this licence.
  2. Trains cancelled by planned engineering works are not counted as a cancellation. (As long as they are removed from the timetable.)
  3. Rail replacement buses are not counted, since running information is not available.
  4. Trains running within two minutes of correct time are deemed to be on time. I also show trains within five minutes, the railway's standard.