Engineering Works Detail

Sat 19th July 2014 to Sun 31st August 2014
Line Closed Between Chorley and Leyland

The line between Chorley and Leyland will be closed to allow tunnel work at Chorley, bridge rebuilding, and the re-instatement of the Grade II listed 'Chorley Flying Arches'.

First TransPennine Express services will be diverted between Bolton and Preston and will not call at Horwich Parkway, Chorley, and Buckshaw Parkway.

Northern Rail services are replaced by buses between Bolton and Preston on Saturdays and Sundays, and between Chorley and Preston on weekdays. [237]


National Rail
Information on engineering works is mostly provided by National Rail Enquiries. You are advised to check with National Rail Enquiries for the latest updates before travelling.

Timetable alterations for engineering works are published in two different ways: Some appear as Future Engineering Works on the National Rail web site, while others, especially changes for longer periods, are simply incorporated into the published timetables. The latter are harder to spot and may be missing from this list.