Train Service Performance at Huyton - July 2015
| Date | Scheduled | Trains Run | On Time | Within 5 min. | Comments |
| Wednesday 01 | 162 | 162 | (100.0%) | 122 | (75.3%) | 140 | (86.4%) | |
| Thursday 02 | 162 | 162 | (100.0%) | 144 | (88.8%) | 157 | (96.9%) | |
| Friday 03 | 162 | 162 | (100.0%) | 131 | (80.8%) | 150 | (92.5%) | |
| Saturday 04 | 163 | 163 | (100.0%) | 119 | (73.0%) | 150 | (92.0%) | |
| Sunday 05 | 62 | 62 | (100.0%) | 58 | (93.5%) | 62 | (100.0%) | |
| Monday 06 | 162 | 154 | (95.0%) | 112 | (69.1%) | 130 | (80.2%) | A broken down train between Garswood and Bryn resulted in diversions, delays and cancellations from 12:30 until about 15:00. |
| Tuesday 07 | 162 | 161 | (99.3%) | 138 | (85.1%) | 154 | (95.0%) | |
| Wednesday 08 | 162 | 162 | (100.0%) | 141 | (87.0%) | 157 | (96.9%) | |
| Thursday 09 | 162 | 162 | (100.0%) | 141 | (87.0%) | 157 | (96.9%) | |
| Friday 10 | 162 | 162 | (100.0%) | 138 | (85.1%) | 154 | (95.0%) | |
| Saturday 11 | 163 | 163 | (100.0%) | 139 | (85.2%) | 160 | (98.1%) | |
| Sunday 12 | 62 | 62 | (100.0%) | 55 | (88.7%) | 60 | (96.7%) | |
| Monday 13 | 162 | 162 | (100.0%) | 139 | (85.8%) | 157 | (96.9%) | |
| Tuesday 14 | 162 | 162 | (100.0%) | 138 | (85.1%) | 153 | (94.4%) | |
| Wednesday 15 | 162 | 161 | (99.3%) | 142 | (87.6%) | 160 | (98.7%) | |
| Thursday 16 | 162 | 162 | (100.0%) | 126 | (77.7%) | 156 | (96.2%) | |
| Friday 17 | 162 | 162 | (100.0%) | 135 | (83.3%) | 156 | (96.2%) | |
| Saturday 18 | 163 | 163 | (100.0%) | 125 | (76.6%) | 148 | (90.7%) | |
| Sunday 19 | 62 | 62 | (100.0%) | 60 | (96.7%) | 62 | (100.0%) | |
| Monday 20 | 161 | 161 | (100.0%) | 120 | (74.5%) | 140 | (86.9%) | A broken down train at Huyton caused delays and cancellations between 09:30 and 11:00. |
| Tuesday 21 | 160 | 159 | (99.3%) | 141 | (88.1%) | 155 | (96.8%) | |
| Wednesday 22 | 160 | 160 | (100.0%) | 135 | (84.3%) | 151 | (94.3%) | |
| Thursday 23 | 160 | 158 | (98.7%) | 124 | (77.5%) | 145 | (90.6%) | |
| Friday 24 | 162 | 160 | (98.7%) | 109 | (67.2%) | 132 | (81.4%) | |
| Saturday 25 | 163 | 163 | (100.0%) | 134 | (82.2%) | 148 | (90.7%) | |
| Sunday 26 | 62 | 62 | (100.0%) | 59 | (95.1%) | 61 | (98.3%) | |
| Monday 27 | 161 | 161 | (100.0%) | 134 | (83.2%) | 153 | (95.0%) | |
| Tuesday 28 | 161 | 161 | (100.0%) | 134 | (83.2%) | 152 | (94.4%) | |
| Wednesday 29 | 161 | 161 | (100.0%) | 142 | (88.1%) | 159 | (98.7%) | |
| Thursday 30 | 161 | 161 | (100.0%) | 118 | (73.2%) | 140 | (86.9%) | Delays to Blackpool services between 13:00 and 18:00 were caused by an incident at Leyland. |
| Friday 31 | 162 | 162 | (100.0%) | 133 | (82.0%) | 149 | (91.9%) | |
| Month | 4615 | 4600 | (99.6%) | 3801 | (82.3%) | 4323 | (93.6%) | |
Notes
- The figures are derived from information of Network Rail Infrastructure Limited licensed under this licence.
- Trains cancelled by planned engineering works are not counted as a cancellation. (As long as they are removed from the timetable.)
- Rail replacement buses are not counted, since running information is not available.
- Trains running within two minutes of correct time are deemed to be on time. I also show trains within five minutes, the railway's standard.
|